Project Description
Electrical Upgrade to Mains, Sub-Main Boards and Inclusion of a New ATS to Generator – Racing Science Centre
Customer
QLD Racing Integrity Commission
Project Number
54255
Date of Completion
October 2017
Duration of Project
4 Months
Value of Project
$336,000.00 Ex GST
Project Manager
Matthew Hawker
Man Hours
660 hours
Client Contact
Scope of Works
- Upgrade existing supply from substation to 630A including cabling
- Supply and installation of main switchboard to replace existing
- Incorporate automatic transfer switch within main switchboard
- Supply and installation of full site load Cummins standby generator
- Integrate alarm monitoring to allow for quick notification of onsite alarms direct to client’s mobile phones via text message
- Supply and installation of power factor correction unit
- Supply and installation of DB to replace existing
- Upgrade inline surge filter and diverter to 400A for MSSB
- Conduct all cutover works over one weekend with 2 teams running 12 hour shifts from Friday evening to have site fully operational for Monday