Project Description
Customer
Rio Tinto Alcan Gove
Date of Completion
2015
Duration of Project
8 Months
Value of Project
$1.1M
Project Manager
Tony Arnold
Man Hours
7300
Scope of Works
- Installation of Rail Clamp safety system & PLC/SCADA programming
- Installation of new Operator cabin and Control Interfaces
- Installation of new category 3 Safety System
- Installation of new Hydraulic deflector Chute and controls
- Decommissioning of existing Dust Extraction Plant
- All work were conducted during carefully planned 4 to 8 day shutdowns with close planning and interaction with mechanical contractors and maintenance teams.