Project Description
Customer
Koch Solutions Australia
Project Number
63879
Date of Completion
August 2026
Duration of Project
2 Weeks
Value of Project
$520,000
Project Manager
Oscar Darvill
Man Hours
2,300
Scope of Works
To facilitate the easier replacement of the drag chain and electrical cabling during the slew bearing
replacement, and to allow for future cable replacements of the working cables in the drag chain, an
upgrade to install intermediate junction boxes at the portal side of the drag chain was required. The inclusion of these junction boxes removes the requirement to rollback cabling to the substation.
- Scoping and investigation works during planned shutdowns to verify existing installation and facilitate design and planning.
- Design, manufacturing & FAT of new HV, LV, Communication & Control Junction Boxes.
- Installation of new slew portal junction boxes.
- Disconnection and removal of HV, LV, Communication & Control cabling from existing slew deck junction boxes.
- Installation of new cabling through drag chain between junction boxes.
- HV, LV, control and fibre terminations.
- Quality assurance of installation including 200 ITRs.
- Commissiong support.
- Provide guidance and input to client during planning phase to ensure all work executed in critical 2 week shutdown period.
- RPEQ certification of as built drawings.