Project Description
Customer
Sedgman Pty Ltd
Project Number
54768
Year of Completion
2018
Value of Project
$2,000,000 Ex GST
Project Manager
Tony Arnold
Man Hours
15400 Hours
Client Contact
Available upon request
Scope of Works
Electrical & Instrumentation
- Supply and installation of all Cable Trays and final Pathways
- Supply and installation of Power and Lighting services
- Earth grading rings and testing for MCC
- 11kV reticulation and terminations
- Fibre optic reticulation, termination and testing.
- HV VLF Testing, primary and secondary Injection Testing.
- Temporary 11kV MCC connections and control Cabling.
- Air Conditioning Services installation to MCC
- Installation of 30000m In Field power and control cabling
- Termination of Vendor equipment
- Hazardous Area installations and testing
- QA & T esting via BIM360