Project Description
Customer
Queensland Bulk Terminals
Date of Completion
2015
Duration of Project
6 Month
Value of Project
1.0M
Project Manager
Jim White
Man Hours
8600
Scope of Works
- Decommissioning and removal of redundant Ship Loader
- Design of Electrical and control Systems
- PLC/SCADA Design, Development and programming
- Supply and Installation of Power and control Systems
- Design and Construction of new Ship Loader MCC
- Design and installation of new Remote Operator RF Control System