Project Description
Customer
Sedgman
Project Number
57854
Date of Completion
June 2020
Duration of Project
8 Months
Value of Project
$1,470,000
Project Manager
Tony Arnold
Man Hours
5,780 hours
Client Contact
Ross Smith
Scope of Works
- E&I Services associated with new washed coal transfer conveyor and two feeders
- Installation of new Tramp Magnet
- Installation of new MCC Extension Tier
- Supply and installation of new Stockpile and Gantry Lighting