Project Description
Customer
Aurizon
Project Number
52178
Completion
Oct 2016 – Feb 2017
Duration of Project
6 months
Value of Project
$120,000.00 Ex GST
Client Contact
Stephen Varney
Aurizon Facilities Co-ordinator
Aurizon Facilities Co-ordinator
Phone
Scope of Works
- Manufacture and site installation of new Lighting Control Switch Board for Tower 707
- Manufacture and site installation of External main switch units to existing Lighting Tower DB’s so as one lighting tower can be isolated individually
- Upgrade of lighting control gear to existing Lighting Tower DB’s
- Temporary power to heavy lift fork lift communications equipment during the lighting tower DB upgrade
- Re-lamping of 10 x lighting towers
Note – Aurizon Intermodal Depot is a 24 x 7 operational complex. The lighting towers had operational communications to the container fork lift operators. Power was maintained during the lighting tower upgrade works.
Case Study
This project, at Aurizon’s Intermodal Depot, included the manufacture and installation of switch boards and switch units as well as upgrading lighting control gear to existing towers. The depot is a 24/7 operation with the lighting towers having operation communications to the container forklift operators. Power was maintained throughout the upgrade works.