Project Description
Customer
Downer Infrastructure Services
Project Number
53294
Completion
2017
Duration of Project
4 Months
Value of Project
$1,400,000
Man Hours
15,000
Scope of Works
- Installation, Termination and Testing of 300 sq. mm & 400 sq. mm DC Sub Array Cables at Combiner Boxes & PCUs
- Installation and Connection of Combiner Boxes
- Installation and Connection of 4.0 mm sq. String Cables
- Connection of PV Modules at High Level (4.0 mtrs above grade)
Project Manager
John Deasy
Case Study
With over 15,000 man hours invested into the project over the space of four months, the Arnold team installed, connected and tested cabling for the Sunshine Coast Solar Farm. The solar farm powers the entire electricity consumption of the Sunshine Coast Council across all facilities and operations including administration buildings, community venues, sporting and leisure facilities and holiday parks.