Project Description
Customer
SEDGMAN
Project Number
54768
Date of Completion
2018
Duration of Project
14 weeks
Value of Project
$2.0M
Project Manager
Tony Arnold
Man Hours
15400
Scope of Works
- Supply and installation of all Cable Trays and final Pathways
- Supply and installation of Power and Lighting services
- Earth grading rings and testing for MCC
- 11kV reticulation and terminations
- Fibre optic reticulation, termination and testing
- HV VLF Testing, primary and secondary Injection Testing
- Temporary 11kV MCC connections and control Cabling
- Air Conditioning Services installation to MCC
- Installation of 30000m In Field power and control cabling
- Termination of Vendor equipment
- Hazardous Area installations and testing
- QA & Testing via BIM360